Project Update: February 2022

Project Update: February 2022

SAK will be working in Ruidoso from February 7-12, 2022. They will concentrate at Meander Drive between Paradise Canyon and Reese Drive. The week of February 14-19, the SAK crews will be mobile as they will be retaking videos. Please follow the traffic control signs and all posted information, approach the area with caution, at a very slow speed, and watch for crews.

Read More

Lane Closures and Traffic Control January 3 – January 7, 2022

Lane Closures and Traffic Control January 3 – January 7, 2022

Portions of Main Road, at the roundabout, near Vision Drive, D Street, and 1st Street will be reduced to one lane due to construction for the Phase 2: Lift Stations Project. Please follow the traffic control signs and approach the area with caution, at a very slow speed, and watch for personnel.

Read More

Street Closures: August 30 - September 8, 2021

Street Closures: August 30 - September 8, 2021

The week of August 30 - September 3, 2021, MP Chavez will continue working on the pipe construction located at the intersection of River Trail and Country Club. Tuesday and Wednesday, September 7-8, we will be working on the point of repair located at 103 North Loop. Please look for signs indicating which road and lane will be closed. Approach the area with caution, at a very slow speed, and watch for employees directing traffic.

Read More

Street Closures: August 16 - 19, 2021

Street Closures: August 16 - 19, 2021

Beginning August 16 through August 19 from 6:00 pm to 12:00 am, the Village of Ruidoso will be performing maintenance on the main sewer lines on Mechem Drive from the turnoff to Alpine Village to Sudderth Drive. The road will be one lane throughout Mechem Drive at different areas where the maintenance will be performed (manholes).

Read More

Street Closures: July 27 - August 6, 2021

Street Closures: July 27 - August 6, 2021

Beginning July 27, 2021, crews from MP Chavez will be working on River Trail between Country Club Drive and River Trail on new construction until their anticipated completion on August 6. Please look for signs indicating which road and lane will be closed. Approach the area with caution, at a very slow speed, and watch for employees directing traffic.

Read More

Project Update: June 2021

Project Update: June 2021

The lining crew has finished installing completely, and they will be demobilizing at the end of May. The week of June 1 to June 5 there will be no one from SAK or the manhole crew working locally. The week of June 7 to June 12, the Top Hat crew that seals the liners, as well as the manhole crew, will resume their work schedule. We will continue to keep you posted.

Read More

Street Closures: April 1, 2021

Street Closures: April 1, 2021

On Thursday, April 1, 2021, crews from SAK Construction will be performing maintenance on sewer lines within the Village of Ruidoso. Please look for signs indicating that crews are working and approach the areas with caution. Please reference the following map for specific street and date details. *The SAK Manhole Crew will have a 2 week break from March 20-April 5, 2021.

Read More

Project Update: March 2021

Project Update: March 2021

SAK Construction LLC has begun Construction of Phase 1 Restoration of Existing Sewer Lines and Manholes. This project will rehabilitate the existing sewer piping and manholes that were damaged from the flood. SAK Construction will install a special liner inside the existing sewer main that will renew the sewer quickly and without excavation. They are also working on manhole rehabilitation and final installation of sewer line features.

Read More

Street Closures: March 27, 2021 (Rescheduled from March 27)

Street Closures: March 27, 2021 (Rescheduled from March 27)

On Thursday, March 25, 2021, crews from SAK Construction will be performing maintenance on sewer lines within the Village of Ruidoso. Please look for signs indicating that crews are working and approach the areas with caution. Please reference the following map for specific street and date details. *The SAK Manhole Crew will have a 2 week break from March 20-April 5, 2021.

Read More