Project Update: November 2020
/SAK Construction has begun installing a special liner inside the existing sewer main to renew the sewer quickly and without excavation. Crews will begin this process in the area of Mechem and Sudderth behind Allsup’s.
Crews from SAK Construction have been leaving door hangers with important instructions on residences and businesses that will be affected by the repairs. During this phase of the repair, the liner blocks the connection from homes into the sewer system for anywhere from 4-6 hours. A remote-controlled device will reinstate service to the system once the liner is completely installed. It is important to note that until service is reinstated, the residence or business must refrain from using water as much as possible (minimal restroom usage is acceptable). Since the liner is installed through existing manholes, there may be foot traffic and small equipment in yards that contain manholes.