Updates

Stay informed of community events and updates relevant to the Ruidoso Interceptor Sewer Project.

Ruidoso Sewer Project
  • Home/
  • Project Info/
    • Phase 1 Restoration
    • Phase 2 Lift Stations
    • Phase 3 Hazard Mitigation
  • Resources/
    • Public Presentations
    • Easements
  • Updates/
  • Gallery/
  • Contact/

 

    December 01, 2020

    Street Closures: December 1 - 5, 2020

    December 01, 2020/ Kerry Gladden

    Beginning on December 1, 2020, crews from SAK Construction will be performing maintenance on sewer lines within the Village of Ruidoso. The work will continue through December 5, 2020. Please look for signs indicating that crews are working and approach the areas with caution. See the provided maps for more details.

    Street Closures WeekDec4-5.jpg
    December 01, 2020/ Kerry Gladden/
    Announcement
    Street Closures

    Kerry Gladden

    • Street Closures: December 7 - 12, ...
    • Project Update: November 2020
    • Home/
    • Project Info/
      • Phase 1 Restoration
      • Phase 2 Lift Stations
      • Phase 3 Hazard Mitigation
    • Resources/
      • Public Presentations
      • Easements
    • Updates/
    • Gallery/
    • Contact/

    Ruidoso Sewer Project

    The Ruidoso Sewer Project is a FEMA-funded project that will improve the existing sewer lines from the Upper Canyon in Ruidoso, New Mexico, to the Waste Water Plant.

     

    Stay informed of community events and updates relevant to the Ruidoso Sewer Line Interceptor Project.

    Featured
    Construction Update: May 3, 2024
    May 3, 2024
    Construction Update: May 3, 2024
    May 3, 2024

    Construction update for Phase 3 – Hazard Mitigation and Stabilization Project as of May 3, 2024.

    Read More →
    May 3, 2024
    Featured
    Native Restoration Planting Update: September 13, 2023
    Sep 13, 2023
    Native Restoration Planting Update: September 13, 2023
    Sep 13, 2023

    Native Restoration Planting Update as of September 13, 2023.